Alberta Launches Lower Royalty Program to Spur Oilsands Growth
Alberta is introducing a lower-rate royalty program for oilsands projects, designed to reduce the upfront capital needed for new developments and expansions as the province aims to double output by 2035.
- Program
- Oil Sands Growth Program (OGP)
- Royalty rate
- 2 per cent in the first five years of production, rising by one percentage point a year to 6 per cent in years nine and ten
- Production target
- 8 million barrels of oil a day by 2035; Alberta currently produces around 5 million
- Launch
- Planned for spring; projects announced after 15 November remain eligible
- Review
- Effectiveness to be reviewed in December 2029
How the Program Works
Approved projects get a reduced royalty in their early years. After ten years, or if a company cannot meet production, environmental or regulatory requirements, it returns to the standard royalty regime. Unlike the current plan, the new rate is not tied to West Texas Intermediate oil prices. If the standard rate ends up lower than the incentive rate, the company pays the lower rate. The program does not guarantee approval, and it does not bypass environmental or Indigenous consultation requirements.

The Government’s Case
Premier Danielle Smith said that doubling production will require hundreds of billions of dollars in new investment, and that Alberta is competing with other places, including the United States and Venezuela, for that money. She said the program will lower upfront barriers, particularly as the Pacific Link pipeline needs customers to fill its capacity. Energy Minister Brian Jean said oilsands projects are among the most capital-intensive energy investments in the world and need a competitive fiscal framework.

Who Can Apply
Eligibility is not limited to the five largest oilsands companies that make up the Oil Sands Alliance. Approvals are decided project by project, and can include expansions. The Oil Sands Alliance president said investment conditions have improved over the past year, though regulatory systems still need updating.
Criticism
| Critic | Concern |
|---|---|
| Pembina Institute (oil and gas director Janetta McKenzie) | Questions whether the program is needed, given that the sector is already profitable and benefits from a taxpayer-funded pipeline and recent federal tax measures |
| Same source | Worries that removing price-linked royalty changes could cost Alberta oil revenue, and asks how higher production would affect the environment |
Wider Context
The premier pointed to federal rollbacks, including the cancellation of an oil and gas emissions cap and net-zero power rules, as support for the sector. The oilsands also face a growing wastewater problem, which analysts say will increase as production expands.
This summary is based on a CBC News report published on 13 November 2026. The government’s figures and the critics’ views are as reported. The program has not yet launched.